Hi Neha,
As per the standard SAP system design it will not delete the planned orders of dependent materials if you delete the orders of header materials. You have to re run the MRP for your components only so that it will delete the planned order for your components if it is not firmed. Else you can delete the planned order through MD16.
Regards,